Lumber Company in San Francisco

09/23/2025

Request / Problem

A Bay Area lumber yard needed to upgrade their storage system; fast. They weren't looking for a local supplier; they were looking for a racking partner who could deliver the right cantilever system on a short lead time, regardless of location. The goal was to make better use of the existing yard footprint. The roof supports came out of the design process, the right system for this yard happened to be a cantilever rack built to carry its own overhead coverage.

Solution

Speedrack West designed and installed two separate cantilever systems across two phases, each covering a different section of the yard. Phase 1 used a 20-foot-tall cantilever system with an 8-foot roof overhang, keeping stacked lumber dry without a standalone structure. Phase 2 added a double-sided 18-foot cantilever system with 4 arm levels per column and roof trusses, covering a second section of the yard as inventory expanded. Both systems were built for outdoor exposure from day one.

09/23/2025

Process Overview

01

Phase 1: First Section of the Yard

The client needed weather-protected storage for long lumber on one side of the yard. Speedrack West installed a 20-foot-tall cantilever system with an 8-foot roof overhang, permanent coverage without a separate building.

02

Phase 2: Expanding to a Second Section

As inventory grew, the client came back. Speedrack West installed a double-sided 18-foot cantilever system with 4 arm levels per column and roof trusses in a separate section of the yard, using the same outdoor protection approach as in Phase 1.

  • OUTDOOR

    WEATHER-PROTECTED STORAGE

  • BUILT-IN

    NO TARP MANAGEMENT NEEDED

  • FORKLIFT-READY

    ACCESSIBLE AT HEIGHT

03

Built to Keep Growing

The client has since placed a third order, replacing an older cantilever system in a third section of the yard. Phase 3 is in progress.

......

Talk to a Storage Expert Today

icon blcok
503-640-5666

or

Before
Before
Arrow
After
After
The Main Problems that Speedrack West had Solved

The Main Problems that Speedrack West had Solved

  • WEATHER PROTECTION WITHOUT A SEPARATE BUILDING

    Both systems were engineered with built-in roof structures, an 8-foot overhang on Phase 1, and roof trusses on Phase 2, so lumber stays dry without losing yard space to a standalone structure.

  • STORAGE THAT SCALES WITH THE YARD

    When the first section filled up, Speedrack West came back and built out a second. The yard didn't have to start over; it just expanded.

  • TWO DIFFERENT SYSTEMS, ONE CONSISTENT APPROACH

    Phase 1 and Phase 2 use different heights and configurations because different sections of the yard have different needs. Both are structural, both weather-protected, both built for forklift access.

  • DESIGNED FOR THE SITE, NOT A CATALOG SPEC

    Built the system around this yard's specific weather and space constraints rather than a standard off-the-shelf configuration.

Working with Speedrack West team has been a real pleasure. They made the whole process smooth and straightforward, and we’re 100% planning to come back again—which we actually just did recently.

Other Case Studies

Irving Nieves says: “It's been an easy process working with the Speedrack West team, even with the changes partway through.”

Open full case study

Kyle Gersman says: “I called Bill multiple times a day and he always picked up and was always very helpful. What I really liked is that they pointed out a lot of questions and processes that I didn't even have on my radar going into the move. It helped me expand the scope to an appropriate size of what I needed to consider as we made the transition to a bigger facility.”

Open full case study

Robert Baumgartner says: “Despite picking up this project in the middle of its lifecycle, the transition was flawless thanks to the team’s stellar communication. They exceeded our expectations by delivering the installation earlier than anticipated and hitting every technical requirement. From the sales team’s quick answers to their willingness to make adjustments, the experience was top-tier.”

Open full case study

Consolidated Supply says: “We’re very happy to be your regular client, and it’s always so easy to work with your team”

Open full case study

Derek Patterson says: “I would suggest that there should be no hesitation…from placing an order to getting everything delivered in such a timely manner. I had racking within 7 days compared to 4 to 6 weeks elsewhere. The customer service level is fabulous.”

Open full case study

Levi Littrell says: “It’s a very expensive product no matter who you go with. Speedrack West will actually walk you through the steps and give you pricing options. Definitely, you do your research, but most likely you’re going to come back to Speedrack West.”

Open full case study